"The park is intentionally designed to create opportunities for people of varying ages, abilities and backgrounds to enjoy activities together," Yuma Parks and Recreation Director Eric Urfer told the Yuma Sun about East Mesa Community Park. The project sits at Avenue 6E and 36th Street, a short drive from The Terraces, and the City now expects to finish its first phase in December 2026.
The City's project page still lists the features from the original plan. The Parks and Recreation video updates from August and September show more than that list. Several of the additions are still being built, and a few will be added after the benches go in. Over the next ten weeks, the park will go from a fenced construction site to a finished space in stages you can follow.
The list on the City's page
The official description of Phase 1 covers about 22 acres. It includes a 2-acre lake, fishing pads, a loop trail, a modest amphitheater, picnic areas, restrooms, parking and a large-scale inclusive playground. This description goes back to the groundbreaking ceremony on Friday, January 10, 2025, when the City summarized the same plan in nearly the same words.
The Yuma Sun filled in some numbers. The loop trail is half a mile, and the lake has a fishing pier. The paper also listed a splash pad among the amenities under construction. That one item already goes beyond the City's official list.
Terraces Park, at 2601 E. View Parkway, is the neighborhood's own baseline. The City describes it as a neighborhood park with a playground for children ages 5 to 12, a walking path and open play space. The comparison matters less in size than in which age groups and activities each park serves. East Mesa adds a play area for children ages 2 to 5, along with water, a stage and a place to fish. None of those are at the park on View Parkway.
What the construction videos show
On August 21, 2026, Yuma Parks and Recreation posted an update video titled "Major Progress." Here is what it showed, item by item:
- Landscaping and turf. Landscaping was in place across almost the entire park, and turf was starting to come in.
- Veterans Courtyard. The video calls this "coming along." The remaining work was placing business-sponsored functional art benches, finishing the fencing, and completing a gate between the park and the Veterans Home next door.
- Playground, second layer. The inner core of the playground was nearly complete at the previous update. Crews had moved on to a zip line and a set of swings, and a second swing bay was in place.
- Shade. Shade structures were next, including over the play area for ages 2 to 5, which was already installed.
- Sensory play space. Poured-in-place surfacing and benches were still to come.
- Splash pad. Work was underway.
- Picnic grove. It was nearly complete. Picnic spots will be first come, first served, and visitors may bring their own pop-up canopies.
- Amphitheater stage. It was complete and ready for small performances.
The courtyard, the zip line, the pop-up policy and the gate to the Veterans Home do not appear on the City's project page. They show up only when the Parks staff walk the site on camera.
A second video, posted September 14, 2026, focused on the Sensory Play Zone. It is a sponsored space designed for children of different ages, sizes and abilities. The footage shows play panels set at an accessible height, a sensory spinner, and rollers that children pull themselves through. The surfacing was still waiting for its color layer. The Yuma Sun described the main playground as an inclusive destination playground meant to support a range of physical, sensory and developmental needs, with the sensory area as a dedicated part of it.
Why the opening moved, and what is left
The first phase was originally expected in spring 2026. The Yuma Sun reported the delay and said the City was then aiming for the middle of fall. The City's pages now give December 2026 for both the completion of Phase 1 and the ribbon cutting.
According to Urfer, the remaining work at that point included asphalt for the parking lots and roadways, the last playground features, ramadas, perimeter bollards and signage. After that came final landscaping, public art, site furnishings, testing and commissioning of the park systems, and inspections and punch-list items. Public art is one of the last steps in that list. In practice, the benches are part of the run-up to the opening.
The benches are the last thing to arrive
The Yuma Art Center issued a call to artists for functional art pieces at the park. The project uses a series of Acadia, Arch and Sequoia benches, and each one will be turned into a unique artwork. The City ties the benches to the park's sustainability goals and describes them as functional art made from repurposed materials. Each selected artist receives a $500 stipend and pays for their own supplies. The August video also described the courtyard benches as sponsored by various businesses.
As of today, October 5, 2026, the submission deadline of October 2 has passed. The rest of the schedule is still ahead. It lines up with a busy fall at the Yuma County Fairgrounds on East 32nd Street, a few miles west of The Terraces, so here are both calendars together:
- October 16 to 18. The 5th Annual Fall Fest runs at the Yuma County Fairgrounds, 2520 E. 32nd Street. Gates open at noon each day. Eve 6 plays the main stage Friday at 8 p.m. Saturday has two Paint & Take classes at 1 p.m. and 3 p.m. in the Fine Arts Building, with up to 30 seats each, first come, first served. Sunday brings the demolition derby at 5 p.m., pumpkin carving, and Tropicalisimo Apache at 7 p.m. Admission is $9 for ages 13 and up, $7 for ages 6 to 12, and free for children 5 and under. All featured events are included with entry.
- October 23. The Yuma Art Center notifies the selected bench artists.
- October 31. Scary & Safe runs at the fairgrounds from 5 to 8 p.m., with entrances off 32nd Street. Admission is $1 per person or $5 for a fast pass.
- November. The benches are installed at East Mesa, and the artists begin painting once they are in place.
- December 11 and 12. The Winter Wonder Holiday Soiree, a Yuma Artisans & Crafters Show, fills the fairgrounds' Theatre Building from 9 a.m. to 3 p.m. Admission is free.
- December, date to be announced. East Mesa Community Park holds its ribbon-cutting ceremony.
The City has not published a day or time for the ribbon cutting. The Parks and Recreation YouTube channel has posted every progress update so far, and the City directs questions to the Parks and Recreation Department at (928) 373-5200.
The lake, and what has not been promised yet
The 2-acre lake and its fishing pads are part of Phase 1, and a Yuma Sun photo caption reported the pond as completed. No source has said what fish will be in it or when. Arizona Game and Fish runs a Community Fishing Program that stocks participating waters with catfish in spring and fall, bluegill in spring, and rainbow trout in winter. The agency's Yuma-area directory, last dated April 2025, lists five community fishing waters, and East Mesa is not one of them. That directory was published before the park existed, so its omission says nothing either way. Until the City or the agency announces a stocking plan, the safe expectation is a lake with fishing pads and no confirmed fish.
The later phases are also undated. The City lists a dog park, soccer fields, basketball, tennis and pickleball courts, a futsal mini pitch, an outdoor fitness space, more parking and a maintenance facility. No funding source or construction timeline has been published for them. Phase 1 did lay irrigation infrastructure designed to support those future phases. The City says it bought the parcel specifically for a park, paid for part of it with development fees driven by rapid growth on the east side, and first included the park in its 2016 Parks Master Plan.
For now, the December park will have the lake, the half-mile loop, the splash pad, the zip line, the stage, the picnic grove that allows pop-up canopies, the Veterans Courtyard, and a set of benches that local artists will be painting in November.
The Spencer Property Group follows projects like East Mesa Community Park from groundbreaking to ribbon cutting because east Yuma homeowners ask about them. If you're curious where your Terraces home stands as the park gets close to opening, get your free home valuation and we'll walk through it with you.